BMS Upgrade for NRG Power Plant in Chalk Point, MD

HFC has been commissioned to upgrade the BMS control system for a power plant in Chalk Point, South Carolina. This is a large gas/oil, tangential fired, twin furnace C.E. power plant.

NRG Chalk Point has had HFC equipment installed since 1986 and as technology has advanced over the years has gone through several upgrades, improving plant performance as well as operator interface.

The Final Acceptance Testing (FAT) was completed in Dallas, Texas in August 2019. The current plan for installation of the equipment at the site will be in September 2021.